Banro reports progress at Twangiza

Banro secondary and tertiary crushing plant
Publishing Date
06 Sep 2011 3:29pm GMT
Author
Mining Magazine

Processing  Loading & Hauling  Crushing & Conveying  Drilling & Blasting  


Banro Corp has announced that the construction of its wholly-owned Twangiza Phase 1 gold project in South Kivu Province, DRC, is proceeding on schedule with gold production expected to begin in the December quarter of this year.

'Cold commissioning' - a test run of fluids through the ore processing plant - has now commenced with mechanical commissioning that will proceed to 'hot commissioning' - a test run of low grade ore material through the plant - by mid-September.

Simon Village, Banro’s CEO commented: "We are fast approaching a significant milestone for both Banro and South Kivu province in the DRC. Since Banro's Board made the decision to proceed with development of Twangiza in 2009, we have worked diligently to a fast schedule which has allowed our company to pour its first gold in two years, and with weeks to go, we remain on schedule.

“This event will also signal a tremendous achievement for the South Kivu province as it will be the first new commercial gold mine in the DRC for over half a century - and a testament to the co-operation with the community, government and industry which was necessary for this undertaking."

Activation of the 1.3Mt/y gold production facility follows 24 months of strict deadlines which have been systematically achieved starting with the plant site and construction camp civil excavation works that were completed two months ahead of schedule. The plant capacity is planned to be increased to 1.7Mt/y by mid-2012.

Plant civil construction works are virtually complete while the structural, mechanical, electrical, instrumentation and piping are around 93% complete.

The diesel-powered Aggreko power plant with a design capacity of 7MW is 90% complete and a source of raw water for the processing plant has been secured.

The construction of the tailings management facility is on schedule. Some 350,000t of earth was excavated in the construction of the foundation for the tailings dam wall.

The mine is on schedule to ramp up to full production of around 10,000oz of gold per month early in 2012.

 

 



Companies in this article

Visit the links below to read profiles, see stock information and read all news on companies mentioned in this article.

More News By Subject

Comments

Site Search

Log in
Latest Issue: MM May 2012
MM-May-2012.jpg


 

PROFESSIONAL PLACEMENTS
Professional Placements

Professional PlacementsGeneral Manager Processing - OK Tedi Mining

Ok Tedi Mining Limited operates a world class open pit mine and copper concentrator located in the Western Province of PNG.

Professional PlacementsChief Operating Officer - TiZir Limited

Key Leadership Role with a $600M Joint Venture Project in West Africa, competitive salary package on offer with Residential and FIFO options.

Professional PlacementsChief Executive Officer - Tin International Ltd

Tin International Ltd. (“TIN”) is in the process of becoming an ASX listed tin development company with assets located in Germany.