Cementation Canada to sink new Craig mine shaft

Cementation Canada has been awarded the design and construction of the new internal underground shaft for the Onaping Depth project at Craig mine, part of Glencore’s Sudbury Integrated Nickel Operations (Sudbury INO) in north-eastern Ontario
Cementation Canada to sink new Craig mine shaft Cementation Canada to sink new Craig mine shaft Cementation Canada to sink new Craig mine shaft Cementation Canada to sink new Craig mine shaft Cementation Canada to sink new Craig mine shaft

The deposit is approximately 2,500m below surface and is critical to the long-term sustainability of Sudbury INO’s operations

Staff reporter

PRESS RELEASE: Cementation will design and construct the 7.2m-diameter production shaft. The shaft will be sunk from the 4025 Level of Craig mine and is approximately 1.5km horizontally from the existing Craig shaft.

Cementation will engineer and construct the hoistrooms and underground headframe, and is currently reaming a three-metre-diameter raise bore as a pilot raise for a portion of the final shaft excavation and construction.

"Onaping Depth has been an iconic project for us, and we have worked very closely with Sudbury INO over the years to evaluate and provide the shaft designs and methodology that combine safety with value," said Roy Slack, president of Cementation Canada.

"We are thrilled that the project is going ahead and are very excited to be Sudbury INO's main contractor and design engineer for this shaft project."