290m level development resumes at Lace

DiamondCorp has reported that, following completion of back-filling activities, development tunnelling has resumed on the 290m doming level at the Lace mine in South Africa, almost two weeks ahead of schedule

290m level development resumes at Lace 290m level development resumes at Lace 290m level development resumes at Lace 290m level development resumes at Lace 290m level development resumes at Lace

Tunnelling on the 290m level is now progressing in competent high-grade K4 kimberlite following successful installation of steel arched sets for a 10m section through the centre of the slot drive