MANAGEMENT

Good progress towards start for eCobalt's Idaho

eCobalt’s flagship Idaho cobalt project in east-central Idaho, US, continues to make strides towards its 2020 commercial production target with the advancement of construction and completion of numerous infrastructure items

Staff Reporter
 ICB's tailings waste storage facility and ponds should be completed in September 2018

ICB's tailings waste storage facility and ponds should be completed in September 2018

Company officials that the said the Idaho Cobalt Belt is on time with its schedule and also on budget, with one recently met milestone being the completion of the water treatment plant building foundation and mobilisation of the WTP equipment to the site. Major component placement and the erection of the building steel is set for start on August 18.

Additionally, crews have begun lining the tailings waste storage facility (TWSF) and ponds, targeting September for completion, and have finished connecting the potable water system to the site's administration building.

The power distribution systems to the ponds and wells at the site are also now done, along with the earthworks for the pumpback system. System pipeline installation is now in progress, the company said.

A temporary camp for construction staff has been opened, and a fuel island containment pad is done and its equipment should be installed this month. To date, eCobalt has recorded the pouring of 700 cubic yards/535 cubic metres of concrete at the mine and mill site, or a quarter of all concrete that will be needed for the project.

"Very good progress has been made at the ICP by our exceptional team of mining professionals," president and CEO Paul Farquharson said. "In addition [to being on target for a 2020 start], discussions continue to progress with strong interest from multiple potential off-take partners and project financiers in numerous jurisdictions."

The company is focusing on its goal of clean cobalt concentrate for the battery manufacturing market.

The Idaho cobalt project, located near Salmon, is the only near-term environmentally permitted primary cobalt deposit in the US, according to eCobalt officials. A 2017 feasibility study outlined target production rate of 800 short tons/725.7 tonnes per day and a weighted average annual production of 2.4 million pounds/1.08 million kilograms of cobalt, 3.3 million lbs/1.49 million kg of copper and 3,000 oz/85,000 grams of gold over a mine life of 12.5 years.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production

editions

Mining Magazine Intelligence Automation Report 2023

An in-depth review of operations using autonomous solutions in every region and sector, including analysis of the factors driving investment decisions

editions

Mining Magazine Intelligence Exploration Report 2023 (feat. Opaxe data)

A comprehensive review of current exploration rates, trending exploration technologies, a ranking of top drill intercepts and a catalog of 2022 Initial Resource Estimates and recent discovery successes.