SURFACE

MM's Top 10 technologies: 3

MM highlights the ten technologies that it feels have the greatest potential to bring about a step-change in mining over the next five years

Mining Magazine
Design for directional well placement trajectory at Morenci

Design for directional well placement trajectory at Morenci

3. Directional well placement

Already a staple of the infrastructure, utilities and oil-and-gas industries, directional well placement techniques have the potential to revolutionise certain aspects of mining.

One of the most innovative applications of directional well placement can be seen in open-pit mine dewatering. Schlumberger Water Services together with Freeport-McMoRan has been working to implement a series of oil-and-gas style wells at the Morenci copper mine in Arizona in order to advance the state of play in this arena. MM caught up with the companies to find out more...

Heading in the right direction

Most large open-pit mines eventually encounter groundwater and, depending on their hydrogeological setting, may require proactive mine dewatering. A robust and effective programme is critical to minimising slope instabilities and advance mining.

The impacts of a poorly dewatered mine often include:

  • Wet drilling and blasting, requiring more expensive blasting agents and reduced fragmentation efficiency;
  • Wet working benches, which increase equipment wear and introduce additional safety risk factors;
  • Inundation of the pit floor and slow mine advancement; and
  • Reduced geomechanical performance of pit slopes that in some cases leads to the design of more conservative slope angles, resulting in higher strip ratios and deferral or loss of ore.

For ore deposits in moderate- to high-permeability settings, where wall stability and reducing groundwater inflow are the main dewatering objectives, conventional dewatering is normally implemented with a combination of:

  • In-pit vertical pumping wells to remove storage and lower groundwater levels within the ultimate pit shell;
  • Pit perimeter wells to intercept and remove groundwater moving toward the mine; and
  • A series of sumps and surface pumps to remove standing and near-surface groundwater.

In-pit vertical dewatering wells are often challenging to implement and maintain over the life of the project. They typically have a limited life span  of one or two years due to mine advancement or loss of access, and their vertical orientation limits the opportunity of crossing multiple fault or fracture zones, which are groundwater conduits in a hard-rock aquifer setting.

Additionally, submersible pump run-time is drastically reduced due to operational interruptions leading to less groundwater withdrawal. Maintenance of infrastructure such as piping and surface equipment is also labour-intensive and cumbersome.

The annual costs required to operate a conventional dewatering programme can be significant. Good dewatering results are difficult to attain, and it is common to have groundwater continue to impact mine performance even when a conventional vertical well dewatering programme is implemented.

Pioneering pair

Recognising the limitations of conventional dewatering practices, Schlumberger Water Services and Freeport-McMoRan have collaborated to develop, test and implement a new generation of high-performance mine-dewatering well systems, combining mine hydrogeology and dewatering expertise with cross-over technology from oil and gas directional well placement.

Directional well placement is normal practice for oil and gas production wells. Objectives typically involve maximising hydrocarbon productivity through optimising ‘hydraulic contact’ with the reservoir, accessing resources unreachable with vertical drilling, and minimising the surface footprint of production well drilling and operation.

However, directional well placement in hard-rock mining has a very limited track record and was previously untested for the application of open-pit mine dewatering. The geological and geomechanical environments, size and scale of equipment, flow and production pumping regime, and the associated well design requirements are significantly different.

The technology transfer involves significant adaptation and modification, but Schlumberger and Freeport recognised that the principal benefits of directionally drilled dewatering wells can far outweigh the challenges. Benefits include the ability to:

  • Enhance hydraulic contact between multiple fractures zones and production well/s;
  • Access permeable water-bearing zones unreachable with vertical drilling; and
  • Position the well-heads permanently outside the planned mine operating areas.

The combined impact of these benefits was envisioned to create step-change improvement in dewatering well efficiency, performance and overall effectiveness of the mine-dewatering programme, resulting in significant cost and risk reductions. Anticipated improvements include:

  • Increased well yield due to the design trajectory and enhanced hydraulic contact;
  • Improved well run times with the well-heads located outside of operating areas thereby eliminating the issue of interference between dewatering infrastructure and mine operations;
  • High well yield and improved run times leading to a step-change increase in long-term volumes of groundwater produced from the dewatering programme; and
  • Reduced number of well-head installations with associated burdens of procurement, implementation and interactions with in-pit operation.

Well placement at Morenci

The directional placement of a well to a pre-planned trajectory to accomplish the above goals involves complex interactive consideration of multiple factors. These include the ore deposit geology, geological structure and geomechanical environment, the ranges of performance for directional tooling, downhole surveying, and ability to control and steer the well to the target.

The trade-offs between alternative options, risk factors, the final dewatering goal and overall value to the mine operation are integral to the matrix of planning, design and implementation decisions. Adapting techniques from the oil-and-gas industry, Schlumberger and Freeport developed a mine-dewatering project integration matrix, which was subsequently implemented at the Morenci copper mine in Arizona.

To date, two directionally placed dewatering wells have been successfully implemented at the mine as part of the Garfield open-pit mine-dewatering programme. An initial well was constructed on a ‘proof of concept’ basis and was commissioned in early April 2013.

The well was located on the west wall of the open pit, outside planned mining limits. The borehole was steered underneath the centre of the planned pit on a pre-planned directional trajectory.

Attaining a measured depth of approximately 700m, the well intercepted hydrogeologic targets associated with major northeast-trending geologic structures and hydrogeologic compartments. After completion, the well was equipped with an oilfield-style high-lift, slim-hole electric submersible pump system designed to minimise well drilling and construction hole diameters, while permitting high production pumping rates for variable head pressure conditions.

The well initially produced between 2,461L/min and 2,650L/min (650 and 700gpm), which was at the high end of the planned expectations, and is five to ten times greater than the previously installed in-pit wells.

The well was immediately commissioned into the active dewatering programme and during the initial year operated at 96% availability. The combination of the high production rate and high availability means that it effectively produced up to two orders of magnitude more groundwater than any of the pre-existing in-pit vertical wells, and exceeded the combined groundwater production from the rest of the dewatering system, comprising six vertical production wells.

Following the success of the first well, Freeport and Schlumberger commissioned an additional programme to construct a second well collared on the pit perimeter of the east high wall. The target for the second well was a set of northeast-trending geological structures and lower-permeability compartments.

With a more aggressive drill-bit trajectory, design modifications were made during implementation to control risk while attaining the planned hydrogeological target. Drilling of the second well was recently completed on schedule. Commissioning and performance testing are ongoing, and early results are extremely positive.

Since initiation of the programme, monitoring data has shown a distinct acceleration in the rate of the groundwater level reduction in the open pit. A number of piezometers located within and around the edges of the pit have shown a 60-75m decline in static water elevation.

The companies continue to evaluate the success and value of the programme and are looking for opportunities to implement directional well placement at other mining operations.

Mining Magazine’s top 10 technologies to watch:

1. Rapid development

2. Hard rock cutting for production

3. Directional well placement

4. Tunnel boring machines

5. Laser cutting

6. UAVs and drones

7. 3-D printing

8. Mineral indicators

9. Acid digestion for assaying

10. Microwave and thermal fragmentation

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production

editions

Mining Magazine Intelligence Automation Report 2023

An in-depth review of operations using autonomous solutions in every region and sector, including analysis of the factors driving investment decisions