BASE METALS

Commissioning complete at Hemerdon

Wolf Minerals has completed commissioning of the processing plant at the Drakelands open pit mine constructed at the company’s Hemerdon tungsten and tin project in Devon, southwest England

Ailbhe Goodbody
First concentrate being loaded at Wolf Minerals' Hemerdon project ahead of dispatch to Europe

First concentrate being loaded at Wolf Minerals' Hemerdon project ahead of dispatch to Europe

Construction of the processing plant started on site in March 2014 and wet commissioning of the plant commenced in June 2015. The entire processing plant, and all the equipment within it, has now run successfully...

Start a free trial to continue reading this article
Already have an account?  
Subscribe now

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production

editions

Mining Magazine Intelligence Automation Report 2023

An in-depth review of operations using autonomous solutions in every region and sector, including analysis of the factors driving investment decisions

editions

Mining Magazine Intelligence Exploration Report 2023 (feat. Opaxe data)

A comprehensive review of current exploration rates, trending exploration technologies, a ranking of top drill intercepts and a catalog of 2022 Initial Resource Estimates and recent discovery successes.