PROCESSING

Metso to kit out Neves-Corvo expansion

Metso has won a contract for the Zinc Expansion Project at Neves-Corvo mine in Portugal, owned and operated by Lundin Mining subsidiary Somincor

Staff reporter
Metso is providing a C120 jaw crusher, flotation cells and filter presses for the Neves-Corvo Zinc Expansion Project

Metso is providing a C120 jaw crusher, flotation cells and filter presses for the Neves-Corvo Zinc Expansion Project

PRESS RELEASE: With the Zinc Expansion Project, Lundin Mining expects to expand production from the existing mining areas and from the deeper, higher-grade zinc deposit Lombador Phase 2.

In May 2017, Lundin Mining announced the results of its feasibility study for the Neves-Corvo Zinc Expansion Project, confirming the strong project economics and demonstrating significant incremental value for their Neves-Corvo operations. 

Planning to expand the existing zinc plant from its current capacity of approximately 1.1 million tonnes per year to 2.5 million tonnes, along with further development of Lombador Phase 2, the company signed contracts with Metso in September for the purchase of a C120 jaw crusher, flotation cells and filter presses.

Ore from Lombador Phase 1 and 2 will be extracted using a new materials-handling system, comprising a Metso C120 primary jaw crusher located on the 280-260 level. While developing LP2, the existing zinc plant will be expanded and upgraded. A new 8.5MW SAG mill, previously purchased, will take care of primary grinding, while secondary grinding will be carried out using a repurposed existing mill ahead of new lead and zinc flotation cells. For this, Metso will deliver 19 RCS flotation cells, each with a capacity of 100m³. Upgrades to lead thickening and filtration, water supply and reagent circuits will also be carried out. In this area, two new VPA filters will be installed.

“A better-designed flotation circuit and more filter capacity, along with other changes, will allow for consistently higher throughput,” stated Miguel Santos, regional sales manager from Metso.

Delivery is planned for April 2018. Both surface and underground construction are forecast to be completed by September quarter 2019, and production ramp-up should be completed by the end of that year.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production

editions

Mining Magazine Intelligence Automation Report 2023

An in-depth review of operations using autonomous solutions in every region and sector, including analysis of the factors driving investment decisions

editions

Mining Magazine Intelligence Exploration Report 2023 (feat. Opaxe data)

A comprehensive review of current exploration rates, trending exploration technologies, a ranking of top drill intercepts and a catalog of 2022 Initial Resource Estimates and recent discovery successes.