UNDERGROUND

Nevada Copper board green-lights Pumpkin Hollow construction

Nevada Copper will proceed with construction at its 100%-owned Pumpkin Hollow underground copper project in Nevada, US

Staff Reporter
Nevada Copper has also awarded mining and EPC contracts to Cementation USA and Sedgman USA

Nevada Copper has also awarded mining and EPC contracts to Cementation USA and Sedgman USA

The construction decision is based on a construction capital expenditure estimate of US$197 million for the Pumpkin Hollow underground project, and Nevada Copper continues to expect first concentrate production in the December quarter of 2019.

Pre-construction activities at the site have been ongoing since May 2018, and transition from pre-construction works to full-scale construction of the underground project is expected to commence shortly. The project execution plan includes additional benefits from recent value engineering and detailed design.

Matt Gili, president and CEO of Nevada Copper, said: "We are very excited to commence full-scale construction of the Pumpkin Hollow underground project, which will include the processing plant and completion of the underground mine.

"Delivery of the underground project is the first key step in our strategy of capital-efficient, phased growth from our base in Nevada. I would like to thank all our shareholders and stakeholders, including our financing partners Triple Flag and Red Kite, for their support as we proceed with construction, targeting first copper production in 2019."

In connection with the construction decision, Nevada Copper has awarded a mining contract for shaft sinking and underground mine development work at Pumpkin Hollow to Cementation USA. This follows the earlier pre-works programme carried out by Cementation at Pumpkin Hollow to prepare the existing shaft and hoist infrastructure in advance of commencement of underground construction activities.

In addition, Nevada Copper has awarded an engineering, procurement and construction (EPC) contract for the surface plant and infrastructure to Sedgman USA, a member of CIMIC Group, for a fixed price of US$118 million.

The EPC contract follows several months of a detailed engineering and design programme conducted by Sedgman, incorporating a number of significant improvements to the earlier pre-feasibility study for project published in November 2017.

The fixed price nature of the EPC contract provides Nevada Copper with significant cost protection for project delivery and the use of a leading mineral processing EPC contractor with knowledge of the project further de-risks project execution during ramp-up.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production

editions

Mining Magazine Intelligence Automation Report 2023

An in-depth review of operations using autonomous solutions in every region and sector, including analysis of the factors driving investment decisions

editions

Mining Magazine Intelligence Exploration Report 2023 (feat. Opaxe data)

A comprehensive review of current exploration rates, trending exploration technologies, a ranking of top drill intercepts and a catalog of 2022 Initial Resource Estimates and recent discovery successes.