UNDERGROUND

Ivanhoe to double throughput at Kamoa in mid-2022

The second 3.8-Mtpa concentrator plant expected to begin processing next year.

Ivanhoe to double throughput at Kamoa in mid-2022

Ivanhoe Mines plans to double throughput at its Kamoa-Kakula copper mine in the Democratic Republic of Congo in the second quarter of 2022.

The Phase 2 construction is underway to allow for milling to increase to 7.6 million tonnes per annum. Ivanhoe projects that Phase 1 and Phase 2 combined will produce approximately 400,000 tonnes of copper per year.

Copper concentrate has been produced from the Phase 1 3.8-Mtpa concentrator plant since May, with commercial production achieved on July 1. Commissioning has been completed, after a second filter was installed and commissioned.

A third filter will be installed during the Phase 2 expansion. Construction for the expansion is now more than 60% complete, with the second 3.8-Mtpa concentrator plant expected to start up in the second quarter of 2022.

Ivanhoe Mining is focusing now on erecting and installing the structural steel, platework and piping, as well as the crusher, ball mills, floatation cells, and tailings thickener.

Ivanhoe and its partner Zijin Mining, which both hold an 39.6% interest in Kamoa-Kakula, are considering expediting Phase 3 of concentrator expansion, which would call for a third concentrator plant to be located 10 miles north of the mine. The Phase 3 concentrator would have a larger capacity than the 3.8-Mtpa capacity of Phase 1 and Phase 2 plants.

The Phase 3 concentrator would process ore from the Kansoko Sud deposit, as well as the opening of the Kansoko Central mining area and the Kamoa North area.

The plans also call for upgrading turbine 5 at the Inga II hydropower plant to provide 162 megawatts of hydropower.

A direct-to-blister smelter is under consideration, and would be located near the Phase 1 and Phase 2 concentrator plant. The smelter would use materials produced by the three concentrator plants, and would have a production capacity of 500,000 tpa of blister copper.

The smelter will use technology from Outotec. The next steps will include basic engineering and ordering of equipment.

In an effort to be carbon-neutral, Kamoa-Kakula will be electrifying its mining fleet, which will be powered by hydrogen fuel cells or electric batteries. The mining project staff are also working with mining suppliers to decrease fossil fuel use and use more electric and hydrogen technology. The mine is already powered by renewable hydropower.

At the Western Foreland Exploration project, located around the Kamoa-Kakula project, Ivanhoe has nearly completed building a 60-kilometer road across the western permit area. Fifty-eight kilometers have been cleared, and 46 kilometers have been covered with laterite. The company has added 9.4 kilometers of road to access the southwest foreland.

Ivanhoe has undertaken airborne surveys in the third quarter to delineate drill targets.

Ivanhoe has raised its 2021 copper guidance after copper mine Kamoa-Kakula entered into Phase 1 commercial production in July.

The new copper production guidance is now between 92,500 tonnes and 100,000 tonnes, up from 80,000 tonnes to 95,000 tonnes.

The mine has off-take agreements with CITIC Metal and Zijin subsidiary Gold Mountains International Mining Company Ltd., and include copper concentrate as well as blister copper processed by nearby Lualaba copper smelter.

Kamoa-Kakula has attained profitability in its first operating quarter, recording revenue of US$342.6 million for the joint venture. Ivanhoe Mines generated US$41.4 million in profit from the joint venture.

Exploration and project evaluation expenses came to US$15.7 million in the quarter, compared to US$10 million in the year prior.  

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production

editions

Mining Magazine Intelligence Automation Report 2023

An in-depth review of operations using autonomous solutions in every region and sector, including analysis of the factors driving investment decisions

editions

Mining Magazine Intelligence Exploration Report 2023 (feat. Opaxe data)

A comprehensive review of current exploration rates, trending exploration technologies, a ranking of top drill intercepts and a catalog of 2022 Initial Resource Estimates and recent discovery successes.