MANAGEMENT

Order delays drive up costs for Ascot

The process plant cost also increased by C$8 million due to supply chain pressures and inflation.

This article is 3 years old. Images might not display.

Supply chain delays have driven up costs for Ascot Resources' Premier Gold mine in northwestern British Columbia.

The new capital cost for the mine is estimated to be C$224 million, 27% higher than the March 2021 capital cost estimate.

Indirect and owners costs have increased by C$30 million, due to the increased length of workers needing to stay on-site due to delivery delays and COVID-19.

The cost of the process plant also increased by C$8 million due to supply chain pressures and inflation, Ascot said.

Ascot also had lost several pieces of equipment at sea, and has submitted orders for the re-fabrication of the replacement water treatment plant clarifier and tailings thickener. These should be delivered by April.

Ascot has built in a month-long contingency on this delivery date.

Weather impacts, piping and instrumentation labour productivity, and indirect cost inflation are also to blame for the price increases.

Ascot is still on track to achieve first gold pour in the January quarter of 2023. Mill commissioning is targeted for later in 2022.

Mine construction is 23% complete, and Ascot will focus on underground development of underground operations, as well as the delivery and installation of the new water treatment plant in 2022.

The water treatment plant is expected to be completed by November.

Also slated for this year is the completion of the Cascade Creek diversion channel, the tailings facility earthworks, and the completion of the process plant circuit.

Supply chain pressures and inflation have led to increased construction costs across the sector, Marsh Mining Practice Leader Raul Munoz said.

"What we've seen is that over this year, there have been significant delays not just on construction of new mines, but also with mines that are producing," he said. "There have been significant issues with the shipment of reagents which are useful in processing."

The majority of delays have not affected long-lead items, he said.

Delays in shipments will continue to be affecting mining deliveries for some time.

"It's going to have an impact for the rest of this year, for sure," he said.

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

editions

Automation and Digitalisation Insights 2025

Discover how mining companies and investors are adopting, deploying and evaluating new technologies.

editions

Mining IQ Exploration Insights 2025

Gain exclusive insights into the world of exploration in a comprehensive review of the top trending technologies, intercepts, discoveries and more.

editions

Future Fleets Insights 2025

Mining IQ Future Fleets Insights 2025 looks at how companies are using alternative energy sources to cut greenhouse gas emmissions

editions

Automation and Digitalisation Insights 2024

Exclusive research for Mining IQ Automation and Digitalisation Insights 2024 shows mining companies are embracing cutting-edge tech