ArcelorMittal eyes two pathways to 'green steel'

Commercial-scale trials underway that use sustainable biomass and carbon-rich waste streams

This article is 4 years old. Images might not display.

A demonstration plant in Hamburg that uses DRI and Electric Arc Furnace (EAF) technologies has a targeted start-up of 2023-2025, said the company in its annual report.

The plant will produce 100,000 tonnes of pig iron a year and initially use ‘blue hydrogen', sourced by extracting hydrogen from natural gas, ahead of a shift to ‘green hydrogen', sourced by extracting hydrogen from water via electrolysis.

At ArcelorMittal Dunkirk, the company is also developing a hybrid blast furnace process, which involves using DRI gas injection technology in the blast furnace shaft as well as using gas injection in the blast furnace tuyeres, using plasma technology to create a reducing gas.

At ArcelorMittal Dunkirk a study has been launched to build a large-scale DRI plant, combined with an electric arc furnace.

ArcelorMittal's second pathway towards lower carbon steel is its "Smart Carbon" route which focuses on modifying the way blast furnaces are used.

It currently has " commercial-scale" trials underway that use sustainable biomass or carbon-rich waste streams - as well as carbon capture and use and storage.

ArcelorMittal added that it was also collaborating with 11 partners on a project called Siderwin to build a three-meter industrial cell which will test iron ore reduction via electrolysis in Maizières, France.

Start-up target for key Smart Carbon projects is targeted in 2022.

"The company believes that these initiatives present significant opportunities for the decarbonization of steelmaking," said ArcelorMittal, noting that it plans to target of a 30% reduction in CO2 emissions in Europe by 2030.

Liberia startup

AML added in the report that it has now completed a revised detailed feasibility study for a US$800 million project to add 15 million tonnes of concentrate sinter fines capacity and associated infrastructure to its Liberia plant.

"AML has now completed the revised detailed feasibility study (which was updated in 2019 to apply best available technology and replace wet with dry stack tailings treatment) for building a 15 million tonne concentrator (Phase 2), with aligned mine, concentrate, rail and port capacity," the company said. 

The plan is now to recommence the project in 2021, with first concentrate expected in the fourth quarter of 2023.

It noted that the project is effectively a brownfield opportunity as  85% of the procurement has already been done, with the equipment on site, and 60% of the civil construction is complete.

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

editions

Automation and Digitalisation Insights 2025

Discover how mining companies and investors are adopting, deploying and evaluating new technologies.

editions

Mining IQ Exploration Insights 2025

Gain exclusive insights into the world of exploration in a comprehensive review of the top trending technologies, intercepts, discoveries and more.

editions

Future Fleets Insights 2025

Mining IQ Future Fleets Insights 2025 looks at how companies are using alternative energy sources to cut greenhouse gas emmissions

editions

Automation and Digitalisation Insights 2024

Exclusive research for Mining IQ Automation and Digitalisation Insights 2024 shows mining companies are embracing cutting-edge tech