Kenmare starts processing at Pilivili in Mozambique

Company recently moved the concentrator plant 23km along a purpose-built road.

This article is 5 years old. Images might not display.

The Wet Concentrator Plant B has started production ahead of schedule, after the company recently moved the 7,000t plant and a 1.700t floating dredge 23km along a purpose-built road to  new location within the project area. 

The cost of the move and installation is estimated at over US$106 million and will enable the company to achieve a production rate of 1.2 million t/yr of ilmenite from 2021 at Moma, a 35% increase on last year.

The Moma mine is one of the largest titanium minerals deposits in the world and following the relocation, Kenmare will provide approximately 10% of the global supply of titanium feedstock.

 

 

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

editions

Automation and Digitalisation Insights 2025

Discover how mining companies and investors are adopting, deploying and evaluating new technologies.

editions

Mining IQ Exploration Insights 2025

Gain exclusive insights into the world of exploration in a comprehensive review of the top trending technologies, intercepts, discoveries and more.

editions

Future Fleets Insights 2025

Mining IQ Future Fleets Insights 2025 looks at how companies are using alternative energy sources to cut greenhouse gas emmissions

editions

Automation and Digitalisation Insights 2024

Exclusive research for Mining IQ Automation and Digitalisation Insights 2024 shows mining companies are embracing cutting-edge tech