The commissioning of the final components of the process plant is now complete at Gruyere

Staff reporter

This article is 6 years old. Images might not display.

In particular, the ball mill and gravity circuit are now operational.

Production guidance for 2019 remains at 75,000-100,000oz ounces, with cost guidance to be reviewed when commercial production is declared. Commercial Production is anticipated mid‐way through the six to seven-month ramp‐up period.

Several minor improvements to the operability of the circuit were made during a plant shutdown for the tie-in of the ball mill. All components of the process circuit are now substantially complete and operational.

Gruyere, which is located approximately 200km east of Laverton in Western Australia, is a global Tier 1 gold mine with a long operating life and forecast high margins. Life‐of‐mine average annual production is forecast at approximately 300,000oz/y.

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

editions

Automation and Digitalisation Insights 2025

Discover how mining companies and investors are adopting, deploying and evaluating new technologies.

editions

Mining IQ Exploration Insights 2025

Gain exclusive insights into the world of exploration in a comprehensive review of the top trending technologies, intercepts, discoveries and more.

editions

Future Fleets Insights 2025

Mining IQ Future Fleets Insights 2025 looks at how companies are using alternative energy sources to cut greenhouse gas emmissions

editions

Automation and Digitalisation Insights 2024

Exclusive research for Mining IQ Automation and Digitalisation Insights 2024 shows mining companies are embracing cutting-edge tech