MANAGEMENT

Shaft sinking starts at Platreef

Permanent sinking work has begun on Shaft 1 at Ivanhoe Mines’ Platreef platinum-group metals, nickel, copper and gold mine in South Africa

Staff reporter
Platreef’s Shaft 1 officially licensed for permanent sinking operations

Platreef’s Shaft 1 officially licensed for permanent sinking operations

Shaft 1, which will have an internal diameter of 7.25m, will provide initial access for early underground development at the Flatreef deposit and will be utilised to fast-track production during the first phase of the project.

Following the successful commissioning and licensing of the required equipment, the permanent sinking phase started at a planned, initial rate of 1.8m/d. This is planned to double the current depth of Shaft 1 from 54m to 107m below surface – the point at which the main sinking phase will begin. Ivanhoe expects that the subsequent main sinking phase will advance at an average rate of 2.7m/d until it reaches the planned, final depth at 1,025m below surface in 2018.

Robert Friedland, executive chairman of Ivanhoe Mines, said: “This is an important milestone in the building of a major, new underground mine at Platreef and we are extremely proud of our employees and contractors for the safe and efficient job they have done in transitioning Shaft 1 from the pre-sinking phase to the permanent-sinking phase.”

/

Drilling with a six-boom jumbo drill rig at the bottom of Shaft 1

The Shaft 1 sinking contract, held by Aveng Mining of South Africa, will include the development of two main stations at below-surface depths of 450m and 750m. Shaft 1 is expected to reach the Flatreef deposit, at a depth of 777m, during the September quarter of 2017.

The selected mining areas proposed in Platreef’s current pre-feasibility study mine plan occur at depths ranging from approximately 700-1,200m below the surface.

The Platreef project is a Tier One discovery by Ivanhoe Mines’ geologists on the Northern Limb of South Africa’s Bushveld Igneous Complex, the world’s premier platinum producing region. Ivanhoe Mines owns 64% of the Platreef project through its subsidiary, Ivanplats, and is directing all mine development work.

Early works for the 10m-diameter Shaft 2, the main production shaft with the capacity to hoist 6Mt/y, are planned to begin next year. The headgear design has been completed by South Africa-based Murray & Roberts Cementation.

Work now is complete on the internal electricity substation, which will have a capacity of 5MVA. Construction is underway of the power transmission lines from the main lines of Eskom, the South African public electricity utility, which will be used for shaft sinking. Back-up generators also have been installed to ensure continuous sinking operations in the event of power interruptions.

The new power transmission lines also will provide electric power to an adjacent community near the Platreef project, which currently has no supply of electricity.

/

Construction of the new permanent N11 national road intersection to the Platreef mine site

Other on-site work includes the construction of the permanent road intersection leading to the Platreef project from the N11 national highway, which will assist with management of safe access to the mine.

Ivanplats plans to develop the Platreef mine in three phases: an initial annual rate of 4Mt/y to establish an operating platform to support future expansions; followed by a doubling of production to 8Mt/y; and then a third expansion phase to a steady-state 12Mt/y. At a projected production rate of 12Mt/y, Platreef would be among the largest platinum-group metals mines in the world.

Good progress is being made in advancing the feasibility study for Platreef’s first-phase production scenario toward completion. The study, which began in August 2015, is being managed by principal consultant DRA Global, with specialised sub-consultants including Stantec Consulting, Murray & Roberts Cementation, SRK, Golder Associates and Digby Wells Environmental.

Ivanplats completed a pre-feasibility study (PFS) in January 2015 that covered the first phase of development that includes construction of a state-of-the-art underground mine, concentrator and other associated infrastructure to support initial concentrate production.

The development scenarios describe a staged approach structured to provide opportunities to expand the operation based on demand, smelting and refining capacity and capital availability. As the first phase of development is placed into production, there is expected to be an opportunity to modify and optimise the subsequent phases, allowing for changes to the timing of capacity expansions to suit market conditions.

The planned mining methods will use highly productive mechanisation, including long-hole stoping and drift-and-fill mining. The mined-out areas within the deposit will be backfilled with a paste mixture that utilises tailings from the process plant and cement. The ore will be hauled from the stopes to a series of ore passes that will connect to a main haulage level connected to Shaft 2, where it will be hoisted to the surface for processing.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Magazine Intelligence team.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production

editions

Mining Magazine Intelligence Automation Report 2023

An in-depth review of operations using autonomous solutions in every region and sector, including analysis of the factors driving investment decisions

editions

Mining Magazine Intelligence Exploration Report 2023 (feat. Opaxe data)

A comprehensive review of current exploration rates, trending exploration technologies, a ranking of top drill intercepts and a catalog of 2022 Initial Resource Estimates and recent discovery successes.